Public Awareness Campaign ON Corruption: "United Against Corruption for a Prosperous Pakistan....."

Project Details

Completed development project under the PSDP.

All completed projects Completed project · PSDP S# 3

Establishment of Specialized Medium Range Weather Forecasting Center (SMRFC) and Strengthening of Weather Forecasting system.

Establishment of Specialized Medium Range Weather Forecasting Center (SMRFC) and Strengthening of Weather Forecasting system.
PSDP S# 3

Key facts

Approved cost
Rs.2502.532 Million
Final expenditure
Rs.2502.53 Million
Expenditure during FY 2019-20
Rs.365.785 Million
Date of commencement
September, 2015
Date of completion
June, 2020
Operationalized
Yes
Date of inauguration
N/A
Physical progress

Progress

Overall physical progress100%
Physical progress during FY 2019-2010%

Scope and objectives

Civil Work (radar building & office building), Procurement & Installation of equipment, Recruitment of staff.

Benefits of the project

Further strengthen the forecasting capabilities of PMD
From short range forecast, PMD would be able to issue medium range forecast.

Remarks: Project is operationalized from July, 2020