Public Awareness Campaign ON Corruption: "United Against Corruption for a Prosperous Pakistan....."

Project Details

Completed development project under the PSDP.

All completed projects Completed project · PSDP S# 507

Construction of Accommodation for Abdullah Shah Ghazi Rangers

Construction of Accommodation for Abdullah Shah Ghazi Rangers
PSDP S# 507

Key facts

Approved cost
Rs.2870.49 Million
Final expenditure
Rs.2870.49 Million
Expenditure during FY 2019-20
Rs.227.00 Million
Date of commencement
April, 2007
Date of completion
June, 2020
Operationalized
Yes
Date of inauguration
N/A
Physical progress

Progress

Overall physical progress100%
Physical progress during FY 2019-207.90%

Scope and objectives

To provide office and residential accommodation facilities for Abdullah Shah Ghazi Rangers

Benefits of the project

The project provides residential/ no residential accommodation, administrative as well as working efficiency enhanced manifold and other allied facilities for all officers/ officials of the newly raised wings.

Remarks: NILL