Construction of Burhan-Havelian Expressway (E-35) 29.1 Km
Brief Scope / Objectives of the Project
The project envisages construction of 59.1 km access controlled four lane divided facility / motorway with service roads on either side with allied structures / facilities.
Benefits of the Project
The motorway will link Karachi - Peshawar Motorway with the northern alignment of CPEC i.e. Havelian to Khunjerab
Approved Cost: Rs.34165 Million
Final Expenditure: Rs.28845.82 Million
Expenditure During FY 2019-20: Rs.645.86 Million
Date of Commencement: March, 2015
Date of Completion: November, 2019
Operationalized (Yes/No), if no reasons: Yes
Date of Inauguration (if inaugurated): N/A
Physical Progress (%)
a) Overall |
100% |
b) During FY 2019-20 |
NILL |
Remarks
The project is physically completed and opened for traffic. Funds are required for clearance of liabilities.
PSDP S# 56