Construction of Burhan-Havelian Expressway (E-35) 29.1 Km
Key facts
- Approved cost
- Rs.34165 Million
- Final expenditure
- Rs.28845.82 Million
- Expenditure during FY 2019-20
- Rs.645.86 Million
- Date of commencement
- March, 2015
- Date of completion
- November, 2019
- Operationalized
- Yes
- Date of inauguration
- N/A
Progress
Scope and objectives
The project envisages construction of 59.1 km access controlled four lane divided facility / motorway with service roads on either side with allied structures / facilities.
Benefits of the project
The motorway will link Karachi - Peshawar Motorway with the northern alignment of CPEC i.e. Havelian to Khunjerab
Remarks: The project is physically completed and opened for traffic. Funds are required for clearance of liabilities.