Construction of KKH Phase-II Havelian-Thakot (118.057 KM) Part of CPEC

Construction of KKH Phase-II Havelian-Thakot (118.057 KM) Part of  CPEC
PSDP S# 59

Key facts

Approved cost
Rs.136659.66 Million
Final expenditure
Rs.118137.67 Million
Expenditure during FY 2019-20
Rs.31472.51 Million
Date of commencement
September, 2016
Date of completion
June, 2020
Operationalized
Partly operationalized
Date of inauguration
18th Nov, 2019 Havelian-Mansehra Section
Physical progress

Progress

Overall physical progress100%
Physical progress during FY 2019-20Nil

Scope and objectives

Construction of 120.12 km long Havelian–Thakot expressway. 4 lanes from Havelian to Mansehra (39 km) and 2 lane facility from Mansehra to Thakot (81.12 km).

Benefits of the project

The project will significantly enhance the potential for increased international trade between China and Pakistan and also with the Central Asian Republics.

Remarks: Havalian-Mansehra 39 km section is operational since Nov, 2019.
Mansehra-Thakot section is likely to be opened for traffic soon.