Capacity Enhancement of Frontier Corps Balochistan by Raising of Eight (08) Additional Wings
Key facts
- Approved cost
- Rs.2719.490 Million
- Final expenditure
- Rs.2719.490 Million
- Expenditure during FY 2019-20
- Rs.195.000 Million
- Date of commencement
- December, 2015
- Date of completion
- 30th June 2020
- Operationalized
- Yes
- Date of inauguration
- N/A
Progress
Scope and objectives
To provide residential/ living accommodation, offices, parking, storage for ammunition & explosive, healthcare, Dinning and pure drinking water along with allied facilities for newly raised (08) additional Wings for Frontier Corps Balochistan (North
Benefits of the project
The project provides residential/ no residential accommodation, administrative as well as working efficiency enhanced manifold and other allied facilities for all officers/ officials of the newly raised wings.
Remarks: Initially the project was scheduled for 2 years phasing during October 2015. Due to non release of funds in the schedule phasing, the project moved to cost/ time overrun. An approx 20.00 million was incurred due to price hike of the local market/ non admissibility of escalation charges as already demanded in the review meeting of the project.