Construction of accommodation for 4 x wings at Wacha Bibi, Qamar Isha, Appi Faqir & Dwa Toi (North Waziristan Agency)
Brief Scope / Objectives of the Project
To provide accommodation facilities for employees of wings at Wacha Bibi, Qamar Isha, Appi Faqir & Dwa Toi (North Waziristan Agency)
Benefits of the Project
The project provides residential/ non-residential accommodation, administrative as well as working efficiency enhanced manifold and other allied facilities for all officers/ officials of the newly raised wings.
Approved Cost: Rs.1642.068 Million
Final Expenditure: Rs.1642.068 Million
Expenditure During FY 2019-20: Rs.199.257 Million
Date of Commencement: November, 2015
Date of Completion: 30th June 2020
Operationalized (Yes/No), if no reasons: Yes
Date of Inauguration (if inaugurated): N/A
Physical Progress (%)
a) Overall |
100% |
b) During FY 2019-20 |
14% |
Remarks
NILL
PSDP S# 506